Camps Reservoir

AT A GLANCE

INFORMATION
Client – George Leslie
Duration – 7 Months
Supplied – Circa 1000m3 Plant Hire Contract
HIGHLIGHTS
  • Client Collaboration
  • Technical Expertise
  • Quality Without Compromise

In the summer of 2024, Grange was approached by George Leslie Ltd to supply ready-mix concrete for the construction of a new concrete slipway at Camps Reservoir in South Lanarkshire.

The slipway design incorporated a 13-degree longitudinal gradient and was to be constructed in sequential pours. This geometry imposed specific performance requirements on the concrete, which needed to remain sufficiently workable to allow effective placement and finishing within an acceptable working window, while also maintaining early-age stability to prevent downslope movement during initial setting and curing.

To meet these requirements, a bespoke concrete mix was developed and initially laboratory-tested at Grange’s central laboratory at Kirkburn Industrial Estate. The laboratory trials focused on identifying a suitable plasticiser type and dosage to achieve the required balance between workability retention and early-age cohesion. Following evaluation, Mapeplast N44, a lignosulfonate-based admixture supplied by Mapei UK Ltd, was selected.

Subsequently, full-scale mock-ups replicating the project slope geometry were constructed at Grange Quarry. These were used to carry out mock plant trials in collaboration with engineers from George Leslie Ltd, allowing the mix design and placement characteristics to be validated under site-representative conditions prior to commencement of the works.

Construction commenced in July 2025 and progressed through to completion in December 2025. This project demonstrates Grange’s collaborative approach with clients and consulting engineers, using early-stage technical development, laboratory testing, and site simulation to de-risk complex pours and ensure predictable, high-quality outcomes on challenging civil engineering projects.

The Grange Quarry mobile batching plant was critical to completing the works at Camps Reservoir on programme. Due to the technically challenging works, and the projects unique access restrictions, conventional methods of bringing in concrete were unfeasible. The batching plant ensured concrete was available as and when required, with expert control on timing and quality by Granges own specialist staff. The technical team at Grange were also extremely knowledgeable and able to assist with any queries, such as when working collaboratively in the initial mix design and trial pours. Thanks to Granges batching plant the project also recorded a substantial reduction on vehicle trips and travel time, contributing to the George Leslie’s environmental targets. Overall, the service provided by Grange Quarry was excellent.

Related Works

Stranoch Windfarm

For this project, Grange was invited to supply concrete to the Stranoch Wind Farm, which included several high-volume pours in excess of 800 m³. Volumes of this scale pre...

Douglas Windfarms

During the 2024-2025 period, Grange were selected by AE Yates Ltd and Wills Brothers Ltd to provide fully third-party accredited on-site concrete for three major wind far...

Whitelaw Brae Windfarm

In 2025, Grange were approached by I H Brown regarding the supply of 5,000 m³ of concrete for turbine bases at the Whitelaw Brae Wind Farm in the Scottish Borders. The in...

Aberarder Windfarm

For this project, Grange was invited to supply concrete to the Aberarder Wind Farm. Although the project involved relatively modest pour sizes, Grange used the opportunit...

Didcot Ground Stabilisation

In October 2019 RSD were hired to supply 12,000m3 of PFA Grout for ground stabilisation and piling preparation at an industrial re-development site in Oxfordshire . RSD w...

Agricultural Lime Plant

Grange’s Agricultural Lime (Also known as Agri Lime or Ag Lime) is produced at our Kelhead Quarry. The new Lime producing facility is now up and running. The plant is des...